July 10

With all the rain behind us and the Holiday we are ready to roll once again. June 20 began the the construction of the staging area with next steps beginning the footing excavation. 

 

July 14

Shane Gress and Dalton Dietz of Palmer Construction build the forms for setting the footers next week.

 

Steve Wible , McConnellsburg office manager and Ted Gress of Shelly & Witter are pictured surveying

July 21

Palmer Construction pouring  the concrete footers.